Do the roof before finish paint, a screen cage, or a patio the crew must cross. Those trades leave finished surfaces the roof work will scuff, and a roof that goes on last has to be built around them.
Covering furniture and moving cars is a separate list. Write down the order of the other trades before anyone orders material.
Leave the eaves for after the roof
Paint on the fascia, the soffit, and the wall under the eaves gets bumped and speckled during tear-off. If the painter finishes those surfaces first, you will be touching them up after the new metal is on.
Walls away from the roof edge can be painted on their own schedule. Ask the painter to hold the eaves, the fascia, and the gutter color until the roof and the gutters are done. Bare replacement boards at the edge are easier to paint once than to mask twice.
If an association reviews exterior color, settle the shingle name and the paint color before either trade orders. The two should describe the same house. Changing one after the other has started means a delay.
Put a screen cage or a patio after the roof
A screen enclosure, a lanai cover, or a new paver patio sits where tear-off debris falls and where people need to walk. If the cage is already built tight to the eave, the roof edge above it is harder to reach and easier to damage. The usual order is the roof first, then the cage or the patio surface.
If the cage is already there and cannot come down, say so in the roof scope. Ask how the screens and the frame will be protected, and what happens if a panel is torn. Put that protection in writing before tear-off morning.
A patio that blocks the side yard also blocks the trailer or the dumpster. Either the patio waits, or the roof start date moves. Do not discover that conflict when both crews are in the driveway.
Send each trade the same sequence
Put the order in an email to the roofer, the painter, and the screen or patio contractor: who goes first, which dates are held, and who you call if a date slips. A verbal plan to work around each other puts two trucks in the driveway on the same morning.
Ask the roofer which days the yard has to stay open. A replacement needs that access. Put that access in the schedule you share, well before the material shows up.
If one trade wants to start early, write a new order. A favor that puts ladders on a finished edge, or paint on a fascia about to be pried off, undoes the sequence.
Leave a gap before the next trade uses the new edge
Give the roof a day to be walked and closed up before painters or screen crews lean ladders on the new edge. Ask for the roof walkthrough before the next trade covers the fascia.
Inside work can run on its own calendar unless the two projects share an opening. A new skylight, a relocated fan, or a vent the kitchen remodel needs should be named in both scopes. Everything else in the kitchen can proceed without waiting on shingles.
Keep the invoices together. When you sell, the dates on those invoices show a buyer the order the work was done.
Questions homeowners ask
Can I paint the whole house before the roof?
You can paint walls the roof work will not touch. Leave the fascia, the soffit, and the band under the eaves until the roof and the gutters are finished. Otherwise you are painting those surfaces twice.
Should a new screen cage go up before the roof?
Put the roof on first when the cage will sit under the eave the crew needs to reach. If the cage is already up, ask for protection and for the edge detail in writing before tear-off.
What if the painter and the roofer book the same week?
Move one of them. Two trades on the eaves at once means neither can finish, and the new roof edge is the surface that gets hurt.
Tell us the other trades before the dates are set
If a renovation and a roof are on the same calendar, tell Pinnacle the other trades when you ask for an assessment. The sequence belongs in the proposal before anyone promises a start date.